Yau Ma Tei West
Yau Ma Tei East
Central Tunnel
Ho Man Tin Access Shaft (Completed)
Kai Tak West
Kai Tak East
Buildings, Electrical and Mechanical Works
Remaining Works
合約編號
--
合約標題
--
合同授予日期
--
顧問公司
--
承建商
--
合約金額
--
動工日期
--
預計竣工日期
--
Contract No.
HY/2014/20
Contract Title
Central Kowloon Route - Yau Ma Tei West
Date of Contract Award
25 October 2018
Consultant
Arup - Mott MacDonald Joint Venture
Contractor
Build King - SK ecoplant Joint Venture
Forecast Total of the Prices
HK$3.464 Billion
Starting Date of Contract
01 November 2018
Anticipated Completion Date
2025
Contract No.
HY/2014/08
Contract Title
Central Kowloon Route - Yau Ma Tei East
Date of Contract Award
8 January 2018
Consultant
Arup - Mott MacDonald Joint Venture
Contractor
Build King - SK ecoplant Joint Venture
Forecast Total of the Prices
HK$5.02 Billion
Starting Date of Contract
17 January 2018
Anticipated Completion Date
2025
Contract No.
HY/2018/08
Contract Title
Central Kowloon Route - Central Tunnel
Date of Contract Award
3 July 2019
Consultant
Arup - Mott MacDonald Joint Venture
Contractor
Bouygues Travaux Publics
Forecast Total of the Prices
HK$6.23 Billion
Starting Date of Contract
12 July 2019
Anticipated Completion Date
2024
Contract No.
HY/2014/09
Contract Title
Central Kowloon Route - Ho Man Tin Access Shaft
Date of Contract Award
5 December 2017
Consultant
Arup - Mott MacDonald Joint Venture
Contractor
Nishimatsu Construction Co.
Forecast Total of the Prices
HK$317 Million
Starting Date of Contract
8 December 2017
Completion Date
19 September 2019
Contract No.
HY/2014/07
Contract Title
Central Kowloon Route - Kai Tak West
Date of Contract Award
28 December 2017
Consultant
Arup - Mott MacDonald Joint Venture
Contractor
Gammon Construction Limited
Forecast Total of the Prices
HK$6.24 Billion
Starting Date of Contract
5 January 2018
Anticipated Completion Date
2025
Contract No.
HY/2018/02
Contract Title
Central Kowloon Route - Kai Tak East
Date of Contract Award
10 April 2019
Consultant
Arup - Mott MacDonald Joint Venture
Contractor
Alchmex – Paul Y Joint Venture
Forecast Total of the Prices
HK$1.97 Billion
Starting Date of Contract
23 April 2019
Anticipated Completion Date
2024
Contract No.
HY/2019/13
Contract Title
Central Kowloon Route - Buildings, Electrical and Mechanical Works
Date of Contract Award
8 June 2020
Consultant
Arup - Mott MacDonald Joint Venture
Contractor
Gammon Construction Limited
Forecast Total of the Prices
HK$5.67 Billion
Starting Date of Contract
18 June 2020
Anticipated Completion Date
2027
Contract No.
HY/2023/08
Contract Title
Central Kowloon Route - Remaining Works
Date of Contract Award
15 July 2024
Consultant
Arup - Mott MacDonald Joint Venture
Contractor
Build King – Tung Lee Joint Venture
Forecast Total of the Prices
HK$830 Million
Starting Date of Contract
29 July 2024
Anticipated Completion Date
2028
Yau Ma Tei West (YMTW)
1Connection to the existing
road network in Yau Ma Tei
2Construction of depressed road
3Construction of western landscaped deck
Yau Ma Tei East (YMTE)
1Construction of Yau Ma Tei
access shaft for CT and cut-and-cover tunnel at Yau Ma Tei
2Reprovisioning of a
section of Gascoigne Road Flyover
3Temporary reprovisioning
of affected facilities, e.g. Jade Hawker Bazaar, Maternal and Child Health Centre and Methadone Clinic,
etc.
Central Tunnel (CT)
1Construction of central
tunnel
2Cut-and-cover tunnels at
Yau Ma Tei and Ma Tau Kok
3Foundation of Ho Man Tin
Ventilation Building
Ho Man Tin access shaft (HMTS)
1Construction of Ho Man Tin
access shaft for Central Tunnel
2Ground
investigation
3Horizontal directional
coring
Kai Tak West (KTW)
1Construction of Ma Tau Kok
access shaft for Central Tunnel contract
2Construction of
cut-and-cover tunnel
3Construction of underwater
tunnel and associated temporary reclamation at Kowloon Bay
4Construction of depressed
roads at Kai Tak
5Construction of Kai Tak Promenade near Metro Park Phase 1 and Phase 2A
Kai Tak East (KTE)
1Construction of Kai Tak Interchange, including vehicular bridges, underpasses and at-grade link roads
2Construction of Kai Fuk
Road Footbridge
Buildings, Electrical and Mechanical Works
(BEM)
1Construction of Tunnel
Buildings, i.e. Yau Ma Tei Ventilation Building, Ho Man Tin Ventilation Building, Kai Tak Ventilation
Building and Administration Building, including structure and building services
2Installation of route-wide
tunnel electrical and mechanical works
3Installation of traffic
control and surveillance system
4Construction of tunnel
cladding
5Testing and
commissioning
Remaining Works
1Design and construction of landscaping works at Yau Ma Tei Landscaped Deck, Yau Ma Tei Rest Gardens, North Tree Park and Kai Tak Phase 2B Landscaped Deck
2Improvement of a 300 m section of Kai Fuk Road
3Planting of compensatory trees
4Associated civil works, electrical and mechanical works, road and drainage works, lighting works and establishment works
Progress
1Ventilation adit and excavation of depressed road at Yau Cheung Road works site are under construction.
2Piling works for landscaped deck at Hoi Wang Road works site and bridge deck construction for the connection bridges to the road network at Lin Cheung Road works site are in progress.
Progress
1Construction of cut-and-cover tunnel and bridge piers for the reprovisioned Gascoigne Road Flyover.
2Phase one demolition of Yau Ma Tei Carpark Building was completed.
Progress
1Drill and blast works at Yau Ma Tei access shaft works sites are in progress
2Drill and blast works at Ho Man Tin access shaft works sites are in progress
3Drill and blast works at Ma Tau Kok access shaft works sites are in progress
Progress
1Ho Man Tin Access Shaft –
Completed
Progress
1Ma Tau Kok – Excavation and lateral support works for cut and cover tunnel is in progress.
2Kowloon Bay – Installation of lateral supports for Stage2 Underwater Tunnel is in progress.
3Kai Tak – The installation of road facilities at cut and cover tunnel, depressed road and underpass are in progress.
Progress
1Kai Tak River works site – Bridge deck construction for vehicular bridges across Kai Tak River is in progress
2Kai Tak Interchange works site – Construction of abutment, pier and bridge deck for vehicular bridges and construction of the underpasses and retaining walls are in progress
Progress
1Pre-bored socketed H-pile installation works and pile load tests at Yau Ma Tei Ventilation Building works site have been completed. Excavation and lateral support (ELS) works will be commenced.
2Works at Ho Man Tin Ventilation Building are anticipated to be commenced in the 4th quarter of 2022.
3Pre-bored socketed H-piles at Kai Tak Ventilation Building and Administration building works site are in progress.