Kai Tak West

Summary

Progress

1Structural works for cut-and-cover tunnel are in progress at Ma Tau Kok works site.
2Structural works for stage 2 underwater tunnel are in progress at Kowloon Bay works site.
3Construction of cut-and-cover tunnel, depressed road and underpass at Kai Tak works site were completed.
4Preparation works are in progress at Kai Tak Promenade works site.

Completed Work Site Location and ratio for reference only
Contract No.

HY/2014/07

Contract Title

Central Kowloon Route - Kai Tak West

Date of Contract Award

28 December 2017

Consultant

Arup - Mott MacDonald Joint Venture

Contractor

Gammon Construction Limited

Forecast Total of the Prices

HK$6.24 Billion

Starting Date of Contract

5 January 2018

Anticipated Completion Date

2025