Kai Tak West
Menu
Summary
Progress
1Structural works for cut-and-cover tunnel are in progress at Ma Tau Kok works site.
2Structural works for stage 2 underwater tunnel are in progress at Kowloon Bay works site.
3Construction of cut-and-cover tunnel, depressed road and underpass are in progress at Kai Tak works site.
4Preparation works are in progress at Kai Tak Promenade works site.
Completed
Work Site
Location and ratio for reference only
Contract No.
HY/2014/07
Contract Title
Central Kowloon Route - Kai Tak West
Date of Contract Award
28 December 2017
Consultant
Arup - Mott MacDonald Joint Venture
Contractor
Gammon Construction Limited
Forecast Total of the Prices
HK$6.24 Billion
Starting Date of Contract
5 January 2018
Anticipated Completion Date
2025