Summary

Progress

1Structural works for cut-and-cover tunnel has been finished at Ma Tau Kok works site.
2Construction of stage 2 underwater tunnel has been finished.
3Construction of cut-and-cover tunnel, depressed road and underpass at Kai Tak works site has been finished.
4Construction of Kai Tak Promenade has been finished.

Completed Work Site Location and ratio for reference only
Contract No.

HY/2014/07

Contract Title

Central Kowloon Route - Kai Tak West

Date of Contract Award

28 December 2017

Consultant

Arup - Mott MacDonald Joint Venture

Contractor

Gammon Construction Limited

Forecast Total of the Prices

HK$6.24 Billion

Starting Date of Contract

5 January 2018

Anticipated Completion Date

2025