Summary
Progress
1Electrical and mechanical installation and testing for Yau Ma Tei Ventilation Building is in progress.
2Structural works for Ho Man Tin Ventilation Building is anticipated to be commenced upon completion of the excavation works.
3Electrical and mechanical installation and testing for Kai Tak Ventilation Building and Administration Building is in progress.
Completed
Work Site
Location and ratio for reference only
Contract No.
HY/2019/13
Contract Title
Central Kowloon Route - Buildings, Electrical and Mechanical Works
Date of Contract Award
8 June 2020
Consultant
Arup - Mott MacDonald Joint Venture
Contractor
Gammon Construction Limited
Forecast Total of the Prices
HK$5.67 Billion
Starting Date of Contract
18 June 2020
Anticipated Completion Date
2027