Buildings, Electrical and
Mechanical Works
Menu
Summary
Progress
1Structural works for Yau Ma Tei Ventilation Building is in progress.
2Structural works for Ho Man Tin Ventilation Building is anticipated to be commenced upon completion of the excavation works.
3Structural works for Kai Tak Ventilation Building is in progress. Architectural Builder's Work and Finishes for Administration Building is in progress.
Completed
Work Site
Location and ratio for reference only
Contract No.
HY/2019/13
Contract Title
Central Kowloon Route - Buildings, Electrical and Mechanical Works
Date of Contract Award
8 June 2020
Consultant
Arup - Mott MacDonald Joint Venture
Contractor
Gammon Construction Limited
Forecast Total of the Prices
HK$5.67 Billion
Starting Date of Contract
18 June 2020
Anticipated Completion Date
2027