Yau Ma Tei East
Menu
Summary
Progress
1Construction of cut-and-cover tunnel is in progress.
2Re-provisioning of Gascoigne Road Flyover is in progress.
3Installation of noise enclosures at Gascoigne Road Flyover is in progress.
Completed
Work Site
Location and ratio for reference only
Contract No.
HY/2014/08
Contract Title
Central Kowloon Route - Yau Ma Tei East
Date of Contract Award
8 January 2018
Consultant
Arup - Mott MacDonald Joint Venture
Contractor
Build King - SK ecoplant Joint Venture
Forecast Total of the Prices
HK$5.02 Billion
Starting Date of Contract
17 January 2018
Anticipated Completion Date
2025