Central Tunnel

Summary

Progress

1Drill and blast works at Yau Ma Tei access shaft works sites are in progress
2Tunnel excavation works at Ho Man Tin access shaft works site are completed, and tunnel lining construction is in progress.
3Tunnel excavation works at Ma Tau Kok access shaft works site are completed, and tunnel lining construction is in progress.

Completed Structural works in progress Blasting work site Location and ratio for reference only